Pre-DG (Land Use, TCOT, PAFS, TIA) | - To ensure RRL can accommodate standard roadside tables and additional commuter infrastructure
- To conserve specific roadside trees
- To ensure existing/proposed park/park connector is safeguarded
| - Width of Road Reserve (incl. planting verge within side table)
- Proposed road alignment
- Proposed cycling path alignment as safeguarded on SDCP under MP19
- If applicable:
- URA/MND’s conveyance on Form B
- EIA report
- EMMP
- Wildlife management plan
| - Topo Survey (if applicable)
|
Pre-Submission, Planning and Other Consultations | - To clarify how proposal may affect roadside verges and trees, and/or existing/proposed parks/park connectors
- To advise on greenery provisions and tree conservation
| - Proposal with safeguarded RRL and indicative entrance position and road alignment
- Proposal with Walking & Cycling Plan
- If applicable:
- URA/MND’s conveyance on Form B
- EIA report
- EMMP
- Wildlife management plan
| |
Design Gateway (G1) | - To secure greenery provisions and comment on conservation of trees (may require Certified Arborist report, e.g., recommendations for works near to, but may not directly impact trees)
- To assess impact to existing, or safeguard provision of new, park/park connector
| - Standard roadside greenery provision (e.g., gradient, width, and depth of green verge incl. tree planting verge according to road category)
- Spatial provision for greenery at Covered Linkways/Pedestrian Overhead Bridge
- Conservation of trees/plants (identification, e.g., trees within road reserve, heritage trees, trees identified in TCOT)
- Entrance(s) position and access point(s) location (e.g., for FEA, maintenance, and pedestrians to ensure sufficient clearance for retaining mature roadside trees)
- New Parks/Park connector/Promenade
| - Topo Survey Plan
- Arborist Report (e.g., recommendations for works near to, but may not directly impact trees)
- Services detection plan
- Photos of existing trees (if not in Arborist Report)
|
Piling Gateway (G1.5) (Optional) | - | - | - |
Construction Gateway (G2) | - To ensure dimensions of green verges are compliant with standard requirements/accepted by NParks at Design Gateway (G1)
| - Dimensions of green verges compliant with standard requirements/as approved by NParks at Design Gateway (G1)
- Landscaping scheme for roadside greenery by Applicant
| - |
Independent Submissions | - To finalise details on roadside tree planting and landscaping works, as well as transplanting works
| - Reinstatement works for green verge (without tree planting)
- Landscaping scheme for roadside greenery undertaken by NParks
- Planting Requirements for Covered Linkways/Pedestrian Overhead Bridge
| - Dimensions (length, width) of green verges to aid cost estimate for landscaping works (only if NParks were to undertake works)
- Specifications for trellis planting, green roof, planter boxes for covered linkways/POB (where applicable)
|